Bluegrass technicians scheduled to wire saw for the rocker beam cylinder pier replacement.
Bluegrass technicians scheduled to provide cutting services for segmenting compressor foundation. Foundation measures 39’6” by 17’ at 8’6”, which will be cut horizontally at elevation 112’4” with five vertical cuts. Total cutting is estimated at 1,394 square feet.
Two 120-ton condensers were split in half so that four 60-ton sections could be removed. The diamond wire cut through 27,000 inconel tubes, steel pipes, and steel baffle plates.
Bluegrass technicians diamond wire sawed twenty feet by two feet riser blocks during train traffic, which reduces track time for replacement.
Wiresawed 14 piers and drilled nearly 300 core holes for anchor bolts, removing 121 cubic yards of concrete.
Performed diamond wire sawing to segment (2) 6' diameter piers in less than an hour on a railroad bridge.
Used Brokk robotic hammer to demolish 2, 68' diameter digester lids.
Bluegrass technicians dismantled mooring dolphin in large sections utilizing diamond wire saws with all cuts taking place above the water line. An estimated 1,000 square feet was cut.
Diamond wire sawed track beams including sole plates during plant shut down.
WILLIAMS BROTHERS/TEXAS DOT
Bluegrass technicians dismantled three piers, including two hammerhead piers, at the intersection of Beltway 8 and Interstate 10 west of downtown Houston at elevations up to seventy feet. Four vertical cuts, two per cap were forty-nine square feet with twenty-two #14 bars and fifteen #8 bars. There were four cuts on the columns, which were fifty-six square feet each that have fifty-four #18 bars each. The remaining straddle bent required two vertical cuts sixty square feet each and consisted of forty-four #14 bars each and twelve #11 bars. The two seven feet diameter columns (34.5 sq/ft) were cut once under cap. Total cutting was estimated to be at six hundred seventy-seven square feet.
Pierce Elevated Bridge- Diamond wire sawed 100s of columns in downtown Houston for new bridge utilizing 3-4 saws dialy.
Diamond wire sawed three pairs of concrete slots into the lock walls so that stoplogs could be installed in the slots.
Segmentation of lid by diamond wire saw for modifications to existing tank.
Cored drilled bridge caisson fifty feet deep at four inches in diameter for the Audubon Bridge Project.
For complete bridge project details visit: http://www.timedla.com/bridge/audubon/
dismantle upper structure of stadium for removations
Bluegrass technicians used four robotic hammers around the clock to demolish six feet by twenty-six feet diameter area that consisted of concrete, granite blocks, and brick from the railroad bridge turnstile pier for installation of new support system.
Read more about the project at ENR.com:
http://enr.construction.com/news/transportation/archives/071107b.asp
Stadium renovations.
Bluegrass technicians demolished the existing stage in The Southern Theatre with robotic hammers to be replaced with an upgraded hydraulic drop stage.